About Us: What Is The 2Hour House?
The 2Hour House is a remarkable example of how we can all learn to turn an impossible to an IS possible! Innovation, creative thinking, and break-thru strategies for managing our lives is the core of this exciting new program.
With his creativity, realization, and vision of what IS possible, Brian Conaway was able to plan and execute the construction of a 2300 square foot house from the ground up, in an unbelievable 2 hours and 52 minutes -- while exceeding all local building code requirements, and setting a new world record. By using many of the techniques now detailed in 2Hour House, Brian succeed by simply refusing to accept the obvious fact that no one can build a house in a little over two hours.
The 2Hour House is the ultimate event based, project management process – designed to change our understanding and acceptance of existing leadership, teambuilding, management expectation. It shifts the global mindset from ordinary to extraordinary, and inspires us to begin breaking the rules, so we can all break records in our business and personal lives.
Records and "Rules" broken with the 2Hour House process:
| The rules say : |
2 Hour House: |
| • It takes a day to set the forms, dig footings and set steel. |
8 min |
| • It takes a half a day to rough-in the plumbing. |
7min |
| • It takes a day to pour and finish concrete. |
40min |
| • It takes several hours to pop the lines before setting walls. |
10min |
| • It takes at least a day to frame the walls. |
15min |
| • It takes a day to rough-in the electrical. |
15min |
| • It takes a day to put in the wall plumbing. |
15min |
| • It takes a day to shingle the roof. |
30min |
| • It takes a half a day to insulate the walls and attic. |
10min |
| • It takes at least a day to sheetrock. |
15min |
| • It takes at least four days to tape, bed, and texture the walls. |
20min |
| • It takes two days to paint. |
10min |
| • It takes a half a day to install the flower beds and trees. |
10min |
| • It takes a day to do the final grade. |
10min |
| • It takes a day to lay the grass. |
10min |
| • It takes a day to set the kitchen cabinets. |
15min |
| • It takes a day to set the bathroom cabinets. |
10min |
| • It takes a day to install the heating and cooling. |
10min |
| • It takes a day to do the interior doors and base boards. |
15min |
| • It takes a half a day to install the garage door. |
3min |
| • It takes a half a day to put in the countertops. |
10min |
Read our Frequently Asked Questions to Learn More
|